Blende18.2 schrieb:
GinaChris schrieb:
Unfortunately work has come to a stand still as the special machine BT45 Driller has broken. A replacement has been ordered but will only arrive at the end of August 2022.
Oh no. Und ich dachte wirklich bis September ist das Dingen komplett save.
Gruß,
Robin
Offensichtlich hat sich das Driller-Problem gelöst, denn Stelle Steward hat am 29. Juli folgendes geschrieben:
UPDATE:
Drill and bits will be purchased tomorrow.
I'll update as soon as work commences .
Stella Stewart
Admin
Am 1. August folgendes Up-Date:
Third Bridge Update
1 August 2022.
Just a few poles still to be laid and of course some tiding up.
They are just awaiting the delivery of the gum poles to complete the construction.
I will let you all know when it can be transversed.
Mr Mafuta and his team have worked 7 days a week when all materials were available.
The absolute STAR has to be the Reserve Manager. She has worked so hard to make this happen.
Even delivering materials and equipment hereself.
Am 3. August dann dies:
Third Bridge Update
3 August 2022.
Yesterday whilst waiting for the gum poles still needed the Team did the railings.
A comparison photo from Monday and yesterday.
Photo Credits: Abednico Kabo Selelo and Mr Mafuta.
4. August:
Third Bridge Update
4 August 2022
The remaining gum poles and other materials needed will be transported to Third Bridge tomorrow.
The Bridge Building Team are having a long overdue visit to their families this weekend.
Work will commence again on Tuesday.
The completion shouldn't take too long to complete now.
Und heute:
Third Bridge Update
7 August 2022.
All gumpoles and other materials arrived at Third Bridge on Friday evening.
Jemand hatte danach gefragt, ob sie/er am 20. August 2022 über die Brücke fahren können und Stella Steward meinte "ja, es sieht so aus".
LG Bele