THEMA: Kazungula Bridge
25 Sep 2018 21:41 #533685
  • travelNAMIBIA
  • travelNAMIBIAs Avatar
  • Beiträge: 30499
  • Dank erhalten: 28348
  • travelNAMIBIA am 25 Sep 2018 21:41
  • travelNAMIBIAs Avatar
Hi Antje,

nur als Ergänzung zu meinem vorherigen Post. Ich hatte das mit Simbabwe u.a. hier her: www.lusakatimes.com/...-bridge-project/amp/

Viele Grüße
Christian
Vom 27. April bis 23. Mai 2024 nicht im Forum aktiv!
Der Administrator hat öffentliche Schreibrechte deaktiviert.
Folgende Benutzer bedankten sich: Rehema
21 Dez 2018 07:29 #543074
  • GinaChris
  • GinaChriss Avatar
  • Beiträge: 4632
  • Dank erhalten: 9485
  • GinaChris am 21 Dez 2018 07:29
  • GinaChriss Avatar
BWgovernment
22 Std. ·
DIVERSION OF TRAFFIC BETWEEN THE BOTSWANA BORDER POST, KAZUNGULA AND THE LANDING BAY ON THE ZAMBEZI RIVER

The General Public is hereby informed that the road from the Botswana Border Post to the Pontoon landing bay on the Zambezi River will be closed on 23rd December 2018. This is to facilitate the ongoing construction of the Kazungula Bridge Access Ramp. Therefore, as from 24th December 2018, all traffic will be required to use the detour road. The detour will be in use until the Kazungula Bridge is completed and opened to traffic.

The detour will require traversing under a section of the new Bridge with a vertical clearance of 6.0m (between the road and the soffit of the Deck). In light of this, high vehicles or those carrying high loads are advised to plan their routes accordingly. Further control measures will be implemented with respect to the number of vehicles within the detour as and when required.

It is advisable that the pedestrians and traffic using the detour approach the area bearing in mind construction activities are in progress. The public is to note that construction traffic has the right-of-way in the area. Furthermore, the public is urged to adhere to the installed signage and to fully cooperate with the flag persons situated along the detour to ensure safe and efficient flow.

Construction activities occurring adjacent to the detour will include earthworks and bridgeworks. These activities necessitate the utilization of earthmoving equipment that must operate within a barricaded area for the public’s safety. Consequently, all road users are encouraged to remain within the defined pathway as directed by the flag persons.

For further information please contact the Project Manager on +267 72 817 828 and Public Relations office at +267 361 2004

Quelle: fb BWgovernment
Gruß Gina
Der Administrator hat öffentliche Schreibrechte deaktiviert.
Folgende Benutzer bedankten sich: freshy, Focus
14 Jan 2019 07:42 #545037
  • travelNAMIBIA
  • travelNAMIBIAs Avatar
  • Beiträge: 30499
  • Dank erhalten: 28348
  • travelNAMIBIA am 25 Sep 2018 21:41
  • travelNAMIBIAs Avatar
"Kazungula Bridge to ease tourist traffic"
www.tourismupdate.co...ease-tourist-traffic

Viele Grüße
Christian
Vom 27. April bis 23. Mai 2024 nicht im Forum aktiv!
Der Administrator hat öffentliche Schreibrechte deaktiviert.
Folgende Benutzer bedankten sich: Logi, mika1606
26 Mär 2019 19:11 #552301
  • GinaChris
  • GinaChriss Avatar
  • Beiträge: 4632
  • Dank erhalten: 9485
  • GinaChris am 21 Dez 2018 07:29
  • GinaChriss Avatar
BWgovernment
1 Std. ·
KAZUNGULA BRIDGE DELAYS BY TEN MONTHS

Completion of the Kazungla Bridge project, initially set for August, is now expected in June next year.

Briefing the Chobe leadership recently, following suspension of work by contractor Daewoo Engineering and Construction, consultants team leader Mr Kobamelo Kgoboko said construction was suspended March 1-10 as well as last week due to late payments.

He said progress was currently at 75.62 per cent as opposed to the planned 86 per cent due to a number of challenges such as suspension of work, slow rate of work and failure to maintain the seven day casting cycle for deck segment.

Other components of the project, he said, the Botswana One Stop Border Post and the Zambian one were currently at 95.9 per cent against the planned 96.8 per cent and 59.86 per cent compared to the revised planned progress of 78.36 per cent respectively.

He explained that the expected completion date for the Botswana post was June instead of May while the Zambian one was anticipated to be complete by December.

Mr Kgoboko said mitigation measures to avoid further delays included encouraging the client, the Botswana and Zambian governments, to pay the contractor promptly and advising the contractor to reduce the cycle time.

For his part, project manager Mr Pius Seone expressed optimism that work at the site would resume soon as the processing of payments on the Zambian side had started.

Mr Seone said he was optimistic that while work was suspended last week as a result of delayed payments, the issue would be promptly addressed.

Chobe MP and also Assistant Minister for Presidential Affairs, Governance and Public Administration, Mr Machana Shamukuni stressed the importance of the project noting that it had created employment.

After completion, he said, it would reduce transit time for freight and passengers, boost the regional economy and even increase global competitiveness of goods from Botswana and Zambia due to reduced time-based trade and transport costs.

Mr Shamukuni said as the district leadership, they found it fit to get first-hand information on the suspension of work at the site.

He, however, clarified that Botswana was up-to-date in terms of payments its partner was still lagging behind.

Mr Shamukuni informed his audience that the Minister of Transport and Communications Ms Dorcas Makgato, in her updates to Parliament, had assured legislators that everything would revert to track.

He said he had no doubt that the issue of late payment would be resolved and work at the site would resume.

Mr Shamukuni implored the district leadership to assure Batswana that all was not lost and that despite the challenges, the bridge would become a reality.

Plateau acting court president, Kgosi Tshegofatso Samoka thanked the team for the update and urged them to keep the employees abreast of developments to avoid confusion.

Plateau Ward councillor, Mr Boitumelo Kanyetu expressed concern that the issue of houses that cracked as a result of the project had been pending for a long time.

In response Mr Seone concurred that the issue had delayed and promised that residents would be called for an update soon. (BOPA)

Quelle: fb BWgovernment

Gruß Gina
Der Administrator hat öffentliche Schreibrechte deaktiviert.
Folgende Benutzer bedankten sich: Reise_Meike, Logi, mika1606
02 Sep 2020 12:08 #594238
  • Champagner
  • Champagners Avatar
  • Beiträge: 7641
  • Dank erhalten: 18332
  • Champagner am 02 Sep 2020 12:08
  • Champagners Avatar
Letzte Änderung: 02 Sep 2020 12:17 von Champagner.
Der Administrator hat öffentliche Schreibrechte deaktiviert.
Folgende Benutzer bedankten sich: freshy, ALM, mika1606
02 Sep 2020 12:46 #594240
  • ALM
  • ALMs Avatar
  • Beiträge: 2280
  • Dank erhalten: 2358
  • ALM am 02 Sep 2020 12:46
  • ALMs Avatar
Ach welche eine Freude... Auch wenn die Nostalgie nach den rostigen Klapperfähren zum Rühren führt.

Alm
Der Administrator hat öffentliche Schreibrechte deaktiviert.